Question 1. A key supplier has just informed the project manager that a component delivery, due today, will arrive two weeks late. How should the project manager classify this situation?
- Option A: A risk, because it may affect the schedule
- Option B: An issue, because it is a current condition that must be dealt with
- Option C: An assumption, because the delivery date was planned
- Option D: A constraint, because it limits the project's options
Show answer and explanation
Correct answer: B. An issue, because it is a current condition that must be dealt with
Risks are uncertain and lie in the future; issues are certain and current. When a risk occurs it becomes an issue, and the response moves from the risk register to the issue log.
- A (incorrect)A risk is an uncertain event that has not happened yet. The delay has already been confirmed.
- B (correct)Correct. The late delivery is already happening, so it is an issue to be logged, owned and resolved.
- C (incorrect)An assumption is something believed to be true for planning purposes. The delivery date may have been an assumption, but the confirmed delay is not.
- D (incorrect)A constraint is a known limiting factor such as a fixed budget or deadline, not an unexpected event during the project.
Reference: PMI: CAPM Examination Content Outline (2023 exam update) (opens in a new tab)

